Work on The Hook play area in Lady Bay starts on 24 November: 14 new pieces of kit, including a 4m climbing net. The park should reopen for Christmas.
The play area at The Hook in Lady Bay is getting more than £100,000 of new equipment, and the council expects it to be finished before Christmas.
Updated 22 November: the council has confirmed that work starts on Tuesday 24 November. It expects the play park to reopen in time for the Christmas holidays, weather permitting.
Rushcliffe Borough Council announced the refurbishment on 26 October. On 20 November it confirmed the start date as 24 November. The work is expected to take “a few weeks”, and the council says the play park should “re-open in time for the Christmas holidays”, weather permitting.
The contractor is Proludic Limited. It will install 14 new pieces of equipment, and several of the existing favourites will stay.
What is being installed
The council’s list of new equipment:
- a large climbing and play unit with a slide
- a four metre high climbing net
- a new maxi slide
- an accessible roundabout for wheelchair users
- new swings, including inclusive seating and a parent-and-toddler swing
- an inclusive play vehicle
- new spring-mounted play equipment
- a sensory play panel
- a “symphony bell bouquet”, an outdoor music feature
- colourful playground markings and games
The masterplan shows the work split across the existing toddler and junior areas, with the new climbing net on the junior side.
Why it matters
The Hook sits between Lady Bay and the River Trent, next to the skate park and basketball court. It is one of the main free places to take young children on that side of West Bridgford.
Cllr Jonathan Wheeler, the council’s cabinet member for leisure and wellbeing, said the site was “such an important facility for the local community”.
“We know how popular this site, along with the adjacent skate park and basketball court, is with local people,” he said.
The council puts its spending on parks and open spaces across the borough at £1 million since 2021. It finished a £30,000 upgrade of the BMX track at Rushcliffe Country Park earlier this month.
What it means for you
- The play area is out of use from 24 November. The council talks of the play park reopening, so plan on the playground being shut while the equipment goes in. It has not said whether the skate park and basketball court next door stay open.
- The skate park and basketball court are not part of the scheme, according to the council’s list.
- The finish date depends on the weather. The council’s own wording is “weather permitting”, so a wet December could push it back.
For more free things to do with children nearby, see our things to do in West Bridgford page.
Have your say